You must be thinking of some other product other and Primavera software. You can assign a calendar to Hammocks in SureTrak, P3, and P6. In addition, you can have any relationship type that you want in any combination with P6 LOE activities
Essentially the common attribute of Hammocks is that their duration is driven by other activities but every software might have a particular implementation on how they work, some software allows for multiple predecessors either ss or ff with the links having their own calendar independent of the predecessors and successors activities.
I do not make much use of hammock activities as when resource loaded the resources are not leveled. Still hammock activities when needed are very useful. The following example reflects the impact of a delay to an activity whose duration varies in function of the delay. A perfect fit for displaying the effect of duration and costs on prolongation claims. The sample is from an actual claim where the job was delayed by the re-design and relocation of one building at the Owner's request.
Landscape maintenance is part of the original contract to start as soon as needed, 10 calendar days after start of landscaping and finish 30 calendar days after finish of job at project delivery. Note resource calendars can be different but must be compatible with activity calendar, using perhaps different workdays while ss lag calendar is in calendar days as required by watering needs and ff lag calendar is in calendar days as defined by the contract. In this job activities were scheduled using regular workweek as per contract, work on week end is not allowed unless asked on time and some reimbursements are done to pay extra inspection costs. The claim is for the difference between 19,200 and 133,200 in this item alone.
Note that resource B might work on other days but landscape maintenance is to be done only on Thursdays and/or Fridays. Here the activity calendar will determine when can B work on the activity.
What is important is that you realize that when transferring data from one software to another or when analyzing other software the behavior of the hammock might differ. Not all software are created equal, keep this always in mind.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Ronald,
You're quite right about assigning calendars to hammocks. Not sure where I got that from.
Original post edited.
Cheers,
G
Gary,
You must be thinking of some other product other and Primavera software. You can assign a calendar to Hammocks in SureTrak, P3, and P6. In addition, you can have any relationship type that you want in any combination with P6 LOE activities
Essentially the common attribute of Hammocks is that their duration is driven by other activities but every software might have a particular implementation on how they work, some software allows for multiple predecessors either ss or ff with the links having their own calendar independent of the predecessors and successors activities.
I do not make much use of hammock activities as when resource loaded the resources are not leveled. Still hammock activities when needed are very useful. The following example reflects the impact of a delay to an activity whose duration varies in function of the delay. A perfect fit for displaying the effect of duration and costs on prolongation claims. The sample is from an actual claim where the job was delayed by the re-design and relocation of one building at the Owner's request.
Landscape maintenance is part of the original contract to start as soon as needed, 10 calendar days after start of landscaping and finish 30 calendar days after finish of job at project delivery. Note resource calendars can be different but must be compatible with activity calendar, using perhaps different workdays while ss lag calendar is in calendar days as required by watering needs and ff lag calendar is in calendar days as defined by the contract. In this job activities were scheduled using regular workweek as per contract, work on week end is not allowed unless asked on time and some reimbursements are done to pay extra inspection costs. The claim is for the difference between 19,200 and 133,200 in this item alone.
Note that resource B might work on other days but landscape maintenance is to be done only on Thursdays and/or Fridays. Here the activity calendar will determine when can B work on the activity.
What is important is that you realize that when transferring data from one software to another or when analyzing other software the behavior of the hammock might differ. Not all software are created equal, keep this always in mind.
Hammock is an activity type from P3 which is similar to P6's "Level of Effort" type.
There are a couple of differences in that you can't assign a calendar to a hammock, and can only use SS and FF relationships
[Edit: You can assign calendars to hammocks. please ignore]
Hi
Check the below link
http://www.htcprojectcontrols.com/TTB2004-6.pdf
Regards
Shahul
Gary,
i am using P6 and i want to know the significance of term "Hammock"
Abhishek,
What software are you using? and what do you want to know?
Cheers,
G