When you are displaying both current project and a baseline bar and select "show relationships" from barchart options, the relationship lines are shown linking the baseline bars and not the current project bars.
Anyone know of a way to fix this?
Cheers,
G
hi gary
this trick is not my idea
i just learned it from one of paul harris' technical papers online last year
http://primavera.com.au/Technical%20Papers/100602_P6V_%20Bars_Tricks_and_Traps.pdf
Thanks, Ferdinand.
-I had just worked it out myself, but your swift reply means none of my colleague's believe me!
Cheers,
G
from bars
move the display name of remaining bar on top of the baseline bar