Manhours and BOQ (Resource) Assignment

S
Syed Ali 👤 Member for 18 years 6 months

Dear All,

Manhours and Unit (Resource) Assignment-in P6 Schedule

I am in process of developing construction schedule (as I will be migrating from P3 to P6) need help on the following:

  1. How can I assign budgeted manhours to activities (Direct+Indierct)
  2. Budgeted Quantity of activity (MTO)
  3. Creation of Calendars with holidays as site will be on rotation 10days works 4days off.

Subsequently Can I generate S curve for above separately?

Can I use earned value of direct manhours to update weekly S curve?

Thanks & regards,

Ali

S
Syed Ali 👤 Member for 18 years 6 months

Thank you. My question was where to assign them in P6 under different resource category of same type of resource i.e. labor I have to assign budgeted manhours and quantity of each activity. Later extract progress and earned value & quantity.

 

Regards,

S
Safak Vural 👤 Member for 18 years

 

Ali,

I think I do not understand your questions. I am not thinking that you are asking about; “from which menus or items you are going to assign resources change calendars and export loadings at P6”.

Sorry I cannot help you.

Regards,

Safak

S
Safak Vural 👤 Member for 18 years

 

Ali,

As far as I understand you want to have basic setup as P3:

- Actual to date = % * BQ

- Link remaining duration with % complete.

So when you enter % of activities after scheduling you can have actual values equals to earned values. Also having single earned value / Baseline S-Curves.

You should use Fixed Duration & Units and also make Duration % same as Units % (or you can update Actual QTY as BQ * % Duration). This will give you earned values and zero variance remaining quantities that you can have S-Curves projections in earned values and monitor SV. Be informed that this way you cannot monitor CV.

I hope I understand your need and help it.

Regards,

Safak

S
Syed Ali 👤 Member for 18 years 6 months

Thanks Safak, I have already gone through P6 102 & 106 courses.

This query popped up because while I assign manhours & qty the default unit/time and budget unit time shown in % is this ok?

Thanks,

Ali

S
Safak Vural 👤 Member for 18 years

Ali,

The subjects you are asking is nearly all course content of PM-102. The course book is hundreds pages.

If you are migrating from P3 you need to study because; Duration Types, % Types, Baselining, Export&Import and reporting (Especially reporting) are quite different and complicated from P3 in first glance.

My recommendation is take at least PM-102 (3 day course) in order to familiarize with software.

Regards,

Safak

 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts