Hi All,
I wonder if you can help using p6.7, have put together schedule but have used two different calenders within the schedule. One calender a Ten day fortnight 9 hr working time the other 7 day calender working 12 hr days.
On the activities using 7 day calender if I put a duration 0f say 19 days for an activity the start and finish dates show a duration of 13 days. I have checked correct calender assigned to correct activity but it still comes out with the same result!
Can anyone throw some light on why this is happening Cheers!
Hi Jeffrey
Check the calendars allocated to your resources.
Best regards
Mike T.
Dear Newman,
Refer the below thread for your query
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/502777/enterprise-calender#comment-65435
Cheers....