IDEAL LINK TYPE FOR SUBCONTRACTOR ACTIVITY AND CLEARANCE

100 Rooms in a floor

"paint works" activity starts after clearance from main contractor

each room clearance is expected in different days

The plan is a floorwised one, having one single bar for "paint works " for a floor

how to secify the clearance in the plan?

as a milstone ? as a bar ? what should be the relationships ??

 

 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Hemanth

The only way to do this properly is to break down the 100 rooms in each floor into sub groups in such number that the painters can work through them without interruption.

For instance if you are using 3 coat work then each room will have to be visited by a painter at least over 3 days.

So if you have 10 blocks of ten rooms and each room has a three day period then the duration for each floor can be broken down accordingly and the logic between rooms / blocks placed FS as required.

You will then have dates when:

1.  Each floor starts

2.  Each room / block starts

If you do not get permission to start on the programme dates you will have immediate information on progress and can report accordingly.

Best regards

Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts