I created a custom field named WF. Then I created and run 2 global changes:
1. Global change 1 (Activities):
user_number6 = WF
2. Global change 2 (Activity Resource Assignment):
Budgeted labor units = user_number6
I already change the security profile but still the Budgeted labor unit is not equal to WF.
Hi,
You will have individually choose each resource and specify the budgete labour/no-labor/material units. Can you please post screenshots of how you are doing it.
Regards
Amit
Check out my blog on Primavera at http://www.primaverablog.in