This is old topic, but I am posting here because I finally allocated time and developed a tool to transfer baseline from one Microsoft Project file to another. It is assumed, that both files represent different versions of the same project schedule.
The limitation of the tool, is that it works on MS Project 2003 and does not work on 2007 and 2010. Reason being is that is uses MS Project feature to save and read project schedule into MS Access format. The feature to save file in MS Access format has been discontinued starting from MS Project 2007.
you have to save the baseline, though literally you can copy & paste the data from the baseline fields (MSP file1)to baseline fields (MSP file2), it will not work even if you make the calculation automatic. The best thing you can do are:
1. make sure both files have the same list of activities/tasks
2. save the interim baseline first for all selected activities in MSP file2 to save the start & finish dates.
3. copy the baseline data from MSP file1 to MSP file2, under fields start, finish, work & cost
4. select all the activities concerned in MSP file2 and save the baseline for selected tasks/activities, be aware for the baseline no. that you are considering.
5. in MSP file2, copy the interim baseline start1/finish1 to the fields start & finish.
as MS Project stores baselines within the project file and not in a separate file as Primavera P3 or AstaDev Powerproject, you cannot transfer a baseline from one project to the other
what you could do is the following
a) open both files,
b) use a table wher baseline fields are displayed
c) make sure both files contain exactly the same list of tasks
d) copy and paste the baseline fields from one task sheet to the other
e) this is a very sensitive work, be sure nobody will disturb you while you are working on it.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
This is old topic, but I am posting here because I finally allocated time and developed a tool to transfer baseline from one Microsoft Project file to another. It is assumed, that both files represent different versions of the same project schedule.
The limitation of the tool, is that it works on MS Project 2003 and does not work on 2007 and 2010. Reason being is that is uses MS Project feature to save and read project schedule into MS Access format. The feature to save file in MS Access format has been discontinued starting from MS Project 2007.
Tool has detailed manual (help file) with it.
It can be downloaded here free of charge: mppbaselinecop.sf.net
Evgeny
Harold,
you have to save the baseline, though literally you can copy & paste the data from the baseline fields (MSP file1)to baseline fields (MSP file2), it will not work even if you make the calculation automatic. The best thing you can do are:
1. make sure both files have the same list of activities/tasks
2. save the interim baseline first for all selected activities in MSP file2 to save the start & finish dates.
3. copy the baseline data from MSP file1 to MSP file2, under fields start, finish, work & cost
4. select all the activities concerned in MSP file2 and save the baseline for selected tasks/activities, be aware for the baseline no. that you are considering.
5. in MSP file2, copy the interim baseline start1/finish1 to the fields start & finish.
Ronald
Harold,
as MS Project stores baselines within the project file and not in a separate file as Primavera P3 or AstaDev Powerproject, you cannot transfer a baseline from one project to the other
what you could do is the following
a) open both files,
b) use a table wher baseline fields are displayed
c) make sure both files contain exactly the same list of tasks
d) copy and paste the baseline fields from one task sheet to the other
e) this is a very sensitive work, be sure nobody will disturb you while you are working on it.
Alexandre