MS-Project - Transfer Baseline from one File to another

Member for

17 years 9 months

This is old topic, but I am posting here because I finally allocated time and developed a tool to transfer baseline from one Microsoft Project file to another. It is assumed, that both files represent different versions of the same project schedule.

The limitation of the tool, is that it works on MS Project 2003 and does not work on 2007 and 2010. Reason being is that is uses MS Project feature to save and read project schedule into MS Access format. The feature to save file in MS Access format has been discontinued starting from MS Project 2007.

Tool has detailed manual (help file) with it.

 

It can be downloaded here free of charge: mppbaselinecop.sf.net

 

Evgeny

Member for

18 years 2 months

Harold,

you have to save the baseline, though literally you can copy & paste the data from the baseline fields (MSP file1)to baseline fields (MSP file2), it will not work even if you make the calculation automatic. The best thing you can do are:

1. make sure both files have the same list of activities/tasks

2. save the interim baseline first for all selected activities in MSP file2 to save the start & finish dates.

3. copy the baseline data from MSP file1 to MSP file2, under fields start, finish, work & cost

4. select all the activities concerned in MSP file2 and save the baseline for selected tasks/activities, be aware for the baseline no. that you are considering.

5. in MSP file2, copy the interim baseline start1/finish1 to the fields start & finish.

Ronald

Member for

22 years 9 months

Harold,

as MS Project stores baselines within the project file and not in a separate file as Primavera P3 or AstaDev Powerproject, you cannot transfer a baseline from one project to the other

what you could do is the following

a) open both files,

b) use a table wher baseline fields are displayed

c) make sure both files contain exactly the same list of tasks

d) copy and paste the baseline fields from one task sheet to the other

e) this is a very sensitive work, be sure nobody will disturb you while you are working on it.

Alexandre