Changing sequence of work in updated programme

S
Sinan Fahmi 👤 Member for 19 years 5 months

Dear Planners,

     while I am updating my programme of work I faced out of sequence activity, my question is that is it possible to change the relation ship of this activity because after scheduling the early finish of this activity is still be driven by its predecessor activity?

 

Thanks in advanced

H
Hadi k. Shabibi 👤 Member for 22 years 4 months

Your can change it if you find the change is necessary during updates, but should be noted and recorded,

list the change in a LOG file and write the reason of the change then send it to client/PM for his record.

J
Jose Frade 👤 Member for 21 years

Hi Sinan

 

Quite often relation of activities have to be changed (most common reason is to reflect a possible change on project management strategie or mitigate some unexpected impact from late completion of activities, etc).

In every case, relation has to be changed and event noted for later reference. Schedule has to be recalculated every time it happens.

 

BR

JMFrade

S
Shah. HB 👤 Member for 17 years 6 months

Hi Sinan Fahmi, PSP

You can revise the relationships if it sounds illogical before updating the program and it has to be recorded for substantiation

Regards

Shahul

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts