As Built Schedule Preparation

Member for

19 years 10 months

Hi Prabu

Shahul is quite correct - you should impact current delays on the current approved programme.

Even if the impacted programme has not been approved you should impact the delay on the original baseline and save the file as "Event 1" to report the delay and then use "Event 1" as the starting point for "Event 2".

Continue to use the Baseline for progress reporting only.

Best regards

Mike Testro

Member for

16 years 11 months

Hi prabu deva

 

If your revised schedule got approved as you mentioned("revised schedule continues to be submitted and approved).Then you can use revised schedule to analysis the impact of delay event and record the length of delay event.

Any ways your revised schedule is developed from your consented baseline schedule with some modifications to incorporate the field conditions and contingencies.

 

Regards

Shahul