Hi All i Need help with these interview Questions Please Helpppppppp Helppppppppppppppp
- Describe the three types of baselines. Primary, secondary and tertiary baselines
- What the difference between primary and project baselines?
- Lists 15 reports that can be generated using primavera P6?
- What discussions usually go on in project update meetings? What were your responsibilities?
- Programme management officer and project management officer what the difference ?
- What is the use of excel in primavera p6?
- What will you do to motivate whoever is responsible to get a project update from them?
- What is the difference between continuous and interruptible scheduling
Top Posters
Sibusiso Mahlalela
0 posts
Dear Geo.
3. you can generate many type of report as you required.
1. Progress report
2. Resource usases report
3. cash flow report.
3 month look a head report
4. monthly report and so on . for detail go to tools, report.
4. In project update meeting we disscuss on the progress og the activity, critical activity, resouce allocation, any stuck activity due to which progress may stop. information need to short out the problem to ensure the stuck activity
Dear Geo
1. Primary baseline is that base line when the project just startred. ie initial base line. secondary baseline or itermidiate base line is that when there is some changes occours in the middle of the project and schedule differs from original base line. It may be due to some addition of activity or deletion of activity. same is the tertiary base line. These base are used for comparision of the base line.
2. after updating the activity or adding the activity you create a new base line (secondary or tertiary). now for comparing you may assign any of the base line (Primary, secondry, tertiary) that base line is the project base line.
Regards\\
KBJ
Dear Geo
1. Primary baseline is that base line when the project just startred. ie initial base line. secondary baseline or itermidiate base line is that when there is some changes occours in the middle of the project and schedule differs from original base line. It may be due to some addition of activity or deletion of activity. same is the tertiary base line. These base are used for comparision of the base line.
2. after updating the activity or adding the activity you create a new base line (secondary or tertiary). now for comparing you may assign any of the base line (Primary, secondry, tertiary) that base line is the project base line.
Regards\\
KBJ