Enterprise-> Calender

M
mani M.R 👤 Member for 16 years 10 months

Hai

In Project Detail option  i Set Default Calender - >7 Days Work Week

& Enterprise Calender -> 7 Days Work Week 

But Still The Summary Bar is Taking Activity Calender(Standard 6 Days Work Week)

In Calender Option-> Used By Also it is Not Showing Project Name

Is there Any Setting I need to Change in Project Detail

a.jpg

Regards

Mani

M
mani M.R 👤 Member for 16 years 10 months

Sir

Thanks for your Valuable Reply

I got it

Regards

Mani

 

 

 

P
Paul Harris 👤 Member for 25 years 1 month

Calendars for Calculating WBS and Other Summary Durations

In Primavera Version 6.2 and ealier the summary duratios were calculated on the Global Default calendar.

In Version 7 the summary durations, including the project duration in the Projects Window are calculated in a similar way as SureTrak:

·         When all the activities in a band share the same calendar then the summary duration is calculated on the calendar of the activities in the band and

·         When they are different the summary duration is calculated on the Project Default calendar.

The picture below has the Project Default calendar set as the 8hr/d & 5d/w and the picture shows that when the calendars are different then the Project Default calendar is used to calculate the summary duration for WBS Nodes, Projects etc:

[[wysiwyg_imageupload:353:]]

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au- a Primavera scheduling software resources site

 

K
kumar s 👤 Member for 16 years 4 months

Dear Mani,

may be due to user preferances time period data,your WBS Summary bar is showing incorrectly.

the WBS Summary also takes this in to consideration while calculating the duration.

so along with the default project and enterprise calendar the user period duaration must also be matching.

like if you want to have 6 day per week calendar in the wbs summary bar then follow the steps

go to edit --user prefernaces---time units ,

if you are working 8 hrs per day then

Hours/day-----8hrs

hours/week--8*6=48hrs

hours/month--48*25=200hrs

hours/year --   2400hrs

 

 

 

M
mani M.R 👤 Member for 16 years 10 months

Hai Moin

Thanks for the Reply

My Problem is Not Activity Calender

My Problem is with WBS Summary Bar Calender

Because P6 will Calculate Original Duration of WBS Summary Bar Based on Project Default Calender

My Project Default Calender & Enterprise Calender  is 7 Days Work week

So My WBS Level 1 Orginal Duration Should be 78 Days (19- March to 04-June) But its Showing 67 Days based on (6 day Work week Calender)

Can u say me How can i Show Orginal Duration as 78 Days

I am using P6.7 Oracle Database

Regards

Mani

 

 

 

M
Moin Khan 👤 Member for 15 years 6 months

Hi Mr.Mani,

as per my understanding i thik you have already assigned 6 days calender to activity and then you have change the default calender to 7 days work week, thats why it is still showing 6 days work week calender.

If this is the condition you can opy for global change or you can just select 6 days calender for one activity and the fill down to rest.

 

regards

moin

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts