Urgent help pls regarding re-scheduling (F9)

G
G T 👤 Member for 15 years 4 months

Dear Forum could u pls help me ... its very utgent...

 

I was given some schedule prepared in P3 so when I reschedule it to some other dates (F9) early activities dont move they are frozen. Data date line keeps moving  but activities not... I even inserted some dummy activities linked to nothing but they stuck at start date and dont move....

 

 

Thanks very much

G

G
G T 👤 Member for 15 years 4 months

Dear Vond it seems it worked ... frozen activities moved (I ll go in datails to see whether everything moved or no) could u briefly explain me what that means ?

 

Dear Gary thanks for ur reply I did as Vond advised (all my activities were early start - none of the actual or something other )

Dear Rafael thabks for ur I think there are to targets in schedule... 

Thank u all... :)

 

G
G T 👤 Member for 15 years 4 months

Dear Vond it seems it worked ... frozen activities moved (I ll go in datails to see whether everything moved or no) could u briefly explain me what that means ?

 

Dear Gary thanks for ur reply I did as Vond advised (all my activities were early start - none of the actual or something other )

 

Thank u all... :)

R
Rafael Davila 👤 Member for 22 years 3 months

Out of curiosity, are you looking at current job bars and date columns or are you looking at target bars and target date columns? At times when we inherit a schedule prepared by others we do not know about some "hidden" settings that might misled us.

Make sure you have a Backup of the file it might be difficult to unschedule the job latter on.

G
Gary Whitehead 👤 Member for 17 years 2 months

You're definitely doing F9 and not CTRL+ F9? check to make sure your CTRL key is not stuck

 

After you schedule, do the activities that are not moving have actual dates or forecast (ie is there an "A" in the dates)?

G
G T 👤 Member for 15 years 4 months

Thanks Vond for your reply ..

but seems didn't work.... :(

V
Vond Kye 👤 Member for 16 years

GT,

Go to schedule icon not the F9 key and then press options > Advance > Uncheck Allow scheduling and levelling of individual projects.

Then on the Project Group Scheduling  Check Replace Project Data dates when scheduling

 

Hope this helps,

 

Cheers,

 

Vond

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts