Milestone - Plant Shutdown Management Process
Milestone
Phase
Origin
Area of Responsibility
Time to Plant
Shutdown Date
Selection of S/D manager
1
Process
Owner
Turnover meeting
1
Process
Outgoing S/D Manager
Initial cost estimate
1
Process
S/D Team
Work breakdown structure
1
Process
S/D Manager
Cost Control Structure
1
Process
Administration
Organizational Breakdown Structure
1
Process
S/D Team
Work list cut-off date
2
Process
S/D Team
Support plans complete
2
Process
Support plan rep
Work Package complete
2
Process
Planning
Master Execution Sched complete
3
Process
Scheduling
Detailed cost estimate
3
Process
S/D Manager
Procurement of materials
3
Process
Procurement
Procurement of machinery
3
Process
Procurement
S/D Readiness Review Audit
3
Process
S/D Team
Plant feed-out
4
Process
Operations
0 months
Plant feed-in
4
Process
Operations
Reports & documents complete
5
Process
S/D Team
Evaluate plant turnaround
5
Process
S/D Team
Postmortem meeting
5
Process
S/D Manager
S/D Summary report
5
Process
S/D Manager
An example of the milestones used for each Shutdown. Activites & Duration is unique to each S/D & processing plant.
In S/D most owners do not allow enough time or resources in the strategic and detailed planning phases to plan properly for the execution phase. This is reflected by the variances between the budget and schedule estimates in the business plan, and the actual cost and schedule duration of the execution phase.
I know that but what i mean sample for shutdown schedule
Shutdowns are usually for short duration and crop-up on short notice, usually breakdown.
Kindly elobrate your job, like which process plant, which dicipline M/E/I.