This Forum is created to discuss the Best practices & issues / concerns for T/A & S/D
- Definition of Turnaround and its phases
- Issues & concerns during T/A planning, implementation & execution phase
- Business requirement for handling the T/A
- Technical features & Evaluation of T/A & S/D Project Management Softwares utilizing latest & proven technology
- Economics & conclusions
There is update at the below link, kindly visit
http://www.planningplanet.com/content/turnaround-shutdown-ta-sd#comment-69565
Hi Mufiz,
Your post is very informative. I am working as Turnaround Planner in one of Canadian Oil and Gas company. I would love to share the way our company looks at Turnarounds. I would like to go back to the fundamental and very first item of your post regarding Turnaround Phases. A Turnaround can be divided into following pahses:
1. Continous planning phase
2. Concept phase
3. Definition phase
4. Detailed Planning Phase
5. Execution Phase
a. Pre-Execution Phase
b. Mechanical Execution Phase
c. Post-Execution Phase
6. Close-Out phase
Time required to complete each Phase depends upon the complexity / magnitude of the scope of turnaround. Set of various activites are performed under each phase to achieve Key deliverables.
Regards
Muhammad Athar Niaz
Hello All,
Why dont you all join this Petro-Chem / Oil & Gas Group and share your experiences with this group of Oil & Gas people.
The Discussion system can let you give your opinion and also recieve email alerts when people add their own content or when they reply to your posts etc.
Heres the link... http://www.planningplanet.com/groups/491358/petro-chem-oil-gas/groupdiscussions
Regards...James
Dear Mufiz Syed.
Good Day..
I am new to Shutdown Planning job and recently completed a Shutdown in LNG Gas Plant. Shutdown is over and now I am asked to calculate the efficeny of the shutdown. What feedback i got from my friends (Planning engineer) is that I should claculate Efficiency of each equipment and that take average of it. And by efficieny what i understand that to calculate it against Actual manhour vs Earned manhours. (as Earned manhours are planned or budgetted manhour at completion). Am i right in my approach in calculating efficiency..?.
Muhammad Atif
Good day Mufiz!
I am a postgraduate student, and now doing dissertation work titled: "Exploring best practice for managing oil and gas turnarounds". Actually i have just started working on it, and a little confused. Now i should define objectives and questions for my dissertation, as the topic is very extensive. But i have challenged with it, because of lack of relative and appropriate information, i do not know how i should start this work, what objectives i should set. Unfortunately, i have no work experience in oil and gas industry, i had just 3 month internship in oil and gas company. I found some books about turnarounds, but they describe only standard methodologies. Can you advice me please may be realtive and useful literature, or some prompts regarding the dissertation topic, it will be really helpful for me. Also i wonder, should i compare in the work different turnaround practices? I mean compare different oil and gas companies' turnarounds?
Thank you.
[[wysiwyg_imageupload:331:]]Turnaround EXECUTION Phases
1. Pre-Shutdown before the Turnaround
After above Lists and group assigned finished. Each section head or Planner has to work out material bill list, service requirement, and overall material cost taking from Warehouse Stock. Then find the overall estimate cost to each line items and adding with 15% to the final total cost as for Turnaround Budget
This has to be done 12 months before the Turnaround
Turnaround Time and Duration Setting
At our company SABIC, T/A is 4 Years Cycle for every individual processing plant, duration has to be considered as below:
With above line items we can find the best starting date and find the longest duration to fit for item #2,#3,#4,#5 or #6 as the duration. But add 5 days time more for Operation as regular size, and add 8 days more for Operation if there is Catalyst require for reduction process before going on service.
Dear Rodney,
In Any T/A or S/D Cost Control starts from preparation stage itself. Following top be considered while building the budget
For more details, kindly refer to the following book ‘Turnaround Management & Turnaround, Shutdown & Outage Management’, both books by Tom Lenahan
Regards
Work list
When a Turnaround/Shutdown is declared the planning group should develop a full list of the existing work as a basis for the "Turnaround/Shutdown Work List".
Additions to the work list should be requested from Operations and Maintenance Groups.
A definition of acceptable Turnaround/Shutdown Work should be issued and all additions must be screened against the definition to ensure that the Work meets the criteria.
Turnaround work is defined as:
Plan for the Plan (Milestone Plan)
The Plan for the Plan is a device used to layout milestone and then monitors the progress of all the elements of Turnaround/Shutdown preparation.
A simple low-level plan is created with an activity for all the elements required to create a Turnaround/Shutdown plan along with all other elements of Turnaround preparation.
These include:
Periodic Turnaround/Shutdown Calendars will be issued, extracted out of the 'Plan for the Plan' to focus on activities due for the coming 2 months. The Turnaround/Shutdown calendar to be updated according to the needs.
Planning Team
A planning team should be formed early in the Turnaround/Shutdown process (normally 18 months before the event) after announcing the Turnaround Manager. The team should be under the control of a Turnaround Planning Leader and should consist of the following:
The team should be sized to ensure the all aspects of the plan and cost estimation can be completed and reviewed in time for test prior to the Turnaround/Shutdown.
Additional Planning support team members should be nominated from each Department / Sections for single point contacts channeling Turnaround/Shutdown related information to the respective sections, represent the Section in Turnaround/Shutdown related meetings and easy resolving of Turnaround/Shutdown related issues.
Indicators of concerns
The following list of "leading indicators" are a good predictor of Turnaround/Shutdown performance – if any of these appear, there is a high likelihood that one or more of the Turnaround/Shutdown objectives will not be met.
Keys to the successful implementation of Plan
PLANNING PRINCIPLES
The function of the planning group in a Turnaround is to identify & locate all aspect of necessary items and prepare all aspects of the work to be executed so that the activity is executed safely at the shortest practical duration and lowest possible cost without affecting quality.
A fully integrated plan is essential for efficient Turnaround Control. This means a detailed Operations Shutdown and Start-up plan, linked to detail Mechanical and project plans to form one cohesive network including Pre-work, of-spec product to on-spec duration and work that can be completed outside of the Turnaround window.
The Plan when complete and reviewed should drive the work using task criticality, rather than monitor progress, (the plan should be pro-active not reactive)
DEFINITION
Turnaround is a planned shutdown of any plant where a large number of activities, in terms of various of discipline have to be executed in a specified / predefined duration. The major challenges in this activity lie with completing the activities and restore the Reliability and Integrity of the facility within the defined premises of duration as per the Corporate Business Plan.
Turnaround entails an extensive seamless planning, resource mobilization and optimization to make it successful in this resourced scarce environment. Typically the planning takes 12 to 18 months for an execution ranging around 2 to 4 weeks hence the whole lifecycle should be considered as a project from its inception to realization. During Turnaround execution the proper monitoring of the whole jobs / activities is required to avoid any delay / slippage from the execution plan.