Dear,
I have the following questions.
milestones to be linked with a final milestone necessarily?
I am doing a Schedule that when linked the final milestone milestones and critical path shows only the final milestone, despite the fact that there are activities that have zero total Float. However when I leave to join if I show how critical path activities with zero total Float. I do not want to warnings showing
http://rapidshare.com/files/453232756/Tunel_de_Quellaveco_Rev14.xer
http://rapidshare.com/files/453232986/Tunel_de_Quellaveco_Rev14_sin_warnings_.xer
Saludos,
JL
Dear,
Solve the problem by establishing a relationship FF intermediate milestones milestone Final
Regards,
Juan Luis