WBS for EPC project (engineering-procurement-contstruction)

Hello friends, I have been asked to develop an EPC work-breakdown. I just completed the construction wbs but i have no ideas about E and P, I am too new in this field. Would you please suggest me an example or an already made structure so I can start working on it and adequate it to my needs?

 

Thank you very much

A
Anoon Iimos 👤 Member for 19 years 9 months

Ideally, you should never develop WBS on your own. It should always be a team effort corresponding to concerned disciplines or specialties. Like for example: You were asked to develop a process flow diagram when you were never a process engineer. So how could you be able to do that? However, reality in construction projects is so difficult to understand or managed. And just ultimately resulting to whatever they can just do best and fast (even copying other works that were totally different from what they intend to do), only to satisfy some stupid contract requirements or not defaulting the contract. So still wondering why most construction projects (if not all) fail? Or always spending beyond budget and always late?

D
dhon bartolome 👤 Member for 15 years 4 months

hi,

Simple WBS

Enggineering 

    > Submissions (Drwgs) 

    > Review and Approval (Drwgs)

Procurement 

   > Submissions (Material/Technical) 

   > Review and Approval (Material/Technical) 

   > P.O 

   > Fabrication/Manufacturing Cycle 

   > Onsite Deliveries 

D
Dinesh Kumar 👤 Member for 20 years 1 month

A raw example (curtailed version) of a typical FPSO project WBS may look like

 

PHASES

                Milestones,Management

                Engg, Proc,  Const

WORK PACKAGES

                Vessel

                Topsides & Process

                Turret & Mooring

                Subsea system etc

AREA/MODULES

                Gas Compression

                Polishing

                K O Drum

              Power Generation / LocEqpRm

                Utilities

                Helideck

DISCIPLINES

                SMP E&I              

MISC

 

Project Name

  1. Milestone

  2. Project Management

  3. Statuary Approvals

  4. ENGINEERING

    1. client deliverables

    2. Detailed dwg development & Approvals

    3. QC documents

  5. PROCUREMENT

  6. CONSTRUCTION

  7. Completion & COMMISSIONING

  8. Load-out / Handover

E
Evaristus Ujam 👤 Member for 16 years 7 months

Just for the sake of emphasis,  your WBS  for engineering and procurement  in a typical  Oil and gas environment may  look like this:

(1) Process, Mechanical, E & I Design

(2) Location (pipe racks, Flare, inlet manifolds, utility area,etc)

(3) Work items (pipes, KOD, Tank, heaters Pumps, valves, etc)

(4) Deliverables(P&IDs, Plot plans, Isometrics, etc)

 

Procurement

(1)Discipline ( Civil/structural, M&E, Instrument)

(2) categories ( local, Foreign)

(3) Shipment (Discuss methology & procurement sequence with experts in procurement Dept)

(4) Work item (equipment, valves, pumps, specialists of diff trades).

Note that process leads in engineering while  Civil structural activities take precedence in most construction activities.

 

Regards

Ujam

 

 

G
Gary Whitehead 👤 Member for 17 years 3 months

wbs = work breakdown structure. the clue is in the name. How do your engineering & procurement departments breakdown their work?

 

They might break it down like the following example, they might not. Speak to them to find out

 

1) Engineering

2) Discipline (civ, mech, elec, etc)

3) Sub-discipline (groundworks, paving, buildings, etc)

4) Area / workfront / whatever you call it

5) Deliverable type (calcs, drawing, survey, etc)

 

1) Procurement

2) Discipline

3) Procurement Item (rebar, piling contractor, etc)

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts