      I want to know the thumb rule for man power planning. For eample:- i am taking 35 hous for detail engineering for equipment design for A1 size, 72 Hous for stress analysis report and so on in my project .similarly i wnat to know the thum rule for construction and erection of steel structure ( manhour per tonne), cable laying ( manhour per metre), Piping erection ( Manhour per inch metre) etc. any refrence or guidence.

 

Regards\\

M
Maxime AUTHIER 👤 Member for 19 years 9 months

Hi Kumar,

 

More info are required to naswer your question, indeed, steel erection ratio will not be the same for erection of stick-built structure or prefabricated pipe rack; manually cable pulling or with electrical winch, piping erection is also function of location (inside unit or on racks)... ... Maybe you can detailed your request

In addition, this will also be impacted by the country, either you know the local average productivity factor or you may need to adapt the ratio based on local feedback.

 

Also, did you look at the rates part of this site, it may contains some.

 

Rgds,

 

Maxime.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts