Summary Tasks Resource Calendars & Tools/Options/Calendar HELP

Hello all,

I want the summary tasks to reflect the amount of time it will take to perform the work under them.  If I have a couple of 24 hr tasks (determined by the task calendar) and some "standard" tasks under the same summary task, I cannot obtain a summary task duration that makes sense.

If I change the calendar in Tools/Options to 24 hours it affects the entire schedule.  Not what I want.

If I apply resources to tasks that are 24 hour resources or standard calendar resources or 10 hour resources, the "calculation" of the summary task duration doesn't make sense.

In setting up a project with many task calendars and unique resource calendars, what will the summary task's duration reflect?  I thought it would describe the amount of time it will take to perform all of the tasks.  But if I look at the start and finish dates and compare those to the summary task's duration it doesn't add up.

Your help is appreciated.

Eric

E
Eric Redding 👤 Member for 16 years 4 months

Hello,

What I have learned in the past hour.  If I have a group of tasks that have different task calendars applied to them, I have to enter the task durations appropriately.  See the first group of tasks below.  This string of tasks should take 7 days.  The next group of tasks has 1 change.  I changed the 24h/day task from 72 hours to 3 days.  MS Project is "thinking" that due to Tools/Options/Calendar that a day equals 8 hours then if the 3 day task is 3x8 and the task calendar says "let's work this task 24 hours straight" then it will take only 1 day to complete.  Left at 72 hours it took, correctly, 3 calendar days. (keep in mind if you are performing 'what-if' challenges to the schedule.  you might want to see the effect of a previously worked 3 day task is you were to apply resources to it working 24 hrs/day remembering that a "day" is defined in Tools/Options/Calendar)

Other groups of tasks below also had one duration change with similar effect.

[[wysiwyg_imageupload:263:height=374,width=449]]

E
Eric Redding 👤 Member for 16 years 4 months

thank you for your response.  The video did not answer my question of having several calendars applied to tasks beneath a summary task and having the summary task correctly display the duration and time interval of the child tasks.

K
Kumar Baiju 👤 Member for 15 years 3 months

Hello Eric

   I have also same problem, you can also see the post in this forum " activity shows only one fourth duration" , you also find the solution.

 

Regards\\

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts