2 Schedules in 1

A
Andrew Tan 👤 Member for 21 years 8 months

Hi,

I need to have a management schedule which is basically 2 months delayed from a contractor schedule.

The client requested for 2 schedule into 1 as the actual are the same.

I am thinking on how to this using planned start or something like that.

Please advise.

 

Thanks,

Andrew

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi Andrew,

As I understand, the client want to see 2 schedules featuring the delay of 2 months.

You may need to Attach the Baseline (Target Schedule) into your current updated schedule. The baseline schedule shall be updated using the "Update Progress" before attaching it. Show the Bars representing the baseline and the current schedule to compare them which will now show the delayed activities.

 

Hope this will help.

 

Regards,

 

Raymund

R
Rafael Davila 👤 Member for 22 years 3 months

This is very common as usually we need a job schedule for management and a schedule for reporting that will not include activities still under negotiation.

We keep the two jobs under separate files, update either one and with a single click of the mouse transfer the actuals from one job to the other as long as you still have a finger without a blister to do the click at the Import Performance from other Project menu selection.

Import actuals

I understand other people transfer the actuals using MS Excel, this I believe should be your option.

Best regards,

Rafael

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts