Global change resource dates

Is there any global change parameters that will align resource start/finish to activity start finish. I have about 300 activities that need alligning and need a quick way to do it. When i tried a global change, it would only affect activities OR activity resource assignments, not a mixture?

R
Raymund de Laza 👤 Member for 16 years 6 months

> make sure that calendar used for the resources is matching with activity calendar.

> make sure that effective date of Resource units and prices is before the start date of the project.

>make sure that resource curve used will distribute resources from the beginning through the end of the duration of the activity.

> Scheudle the project to make sure changes effects.

>Refresh by keying F5.

 

Hope this will help.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts