Exporting from P6.7 to MSP......

B
BRAVE G 👤 Member for 15 years 7 months

Not too confident with this cna anyone Helpppppp

B
BRAVE G 👤 Member for 15 years 7 months

Thanks Guys for For your help You all Farr too Kindddddddddddddd

G
Gary Whitehead 👤 Member for 17 years 2 months

there are normally issues when exporting/importing planning data between different planning software. The kind of issues that typically arise are :

- incomplete long text strings (descriptions, comments)

- different time analysis results for :

- float ( both total and free)

- out-of-sequence updates

- calendars

- different summarised values of PPC (Physical Percent Complete) based on lower level manhours and progress

- code files not always importing (eg WBS)

- incompatible activity types (especially around hammocks)

 

So once you've taken the schedule into MS Project, you need to check it thoroughly before using it. And I wouldn't reccomend doing this on a regular basis.

A
Andy Power 👤 Member for 19 years 9 months

Geoffrey

This depends on which version of P6 and which version of MSP you have.  P6v7 is capable of saving a project in MSP2002/03 XML and MSP 2007 formats and MPX format, P6.2 can save in those formats and MPP.

If you have MSP2003 you can also install the project link element of P6 and this will allow you to open and manage programmes in MSP and save them back to P6, unfortunately I don;t think project link is compatible with later versions of MSP.

Hope that helps.

Andy

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts