Creating ID

Dear All,

How to create Activity IDs according to WBS, can I use Global Change? and how?

 

Regards,

 

Moutaz

R
Raymund de Laza 👤 Member for 16 years 6 months

1. Assign any IDs in the Activity then create a layout with a COLUMN showing the WBS and Activity ID side by side.

2. Do as Simon suggests.

3. Export to Excel the project and Merge WBS and Activity ID in a cell then replace the Activity ID with the merged cell.

4. Manually Type the Activity ID you want in every activity.

 

Hope this will help.

S
Simon Willson 👤 Member for 19 years 6 months

Hi Moutaz,

 

Yes you can combine the WBS with the Activity ID.  You will need to initiate a global change using the following argument:

 

Where

<this will assign the change to all activities>

Then

Activity ID = WBS & Activity ID

Hope this helps.

 

Simon

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts