NEC3 Acceptance of Programme Implications

Member for

11 years 2 months

The accepted programme in now way changes the Works Information.

Member for

15 years 11 months

The schedule is a compendium of what is needed to guide the delivery of a project in terms of time, cost and scope. Quality element as per the resources of materials, equipment and man power may also be reflected. It does not however take the place of specifications, BOQ and drawings which provide more accurate information as contributed by each domain expert, who originate every information that is filtered into the schedule.

If an accepted schedule is discovered at any time to carry any information that contracts any of the contract document sthat preceeded it, such information should be regarded as a bug. The right thing is to do is debug such schedule and make it compatible with every other document considered relevant to the contract.

Ujam

Member for

14 years 11 months

Clause 14.1 states that acceptance of any communication does not transfer liability away from the contractor to comply with his obligations under the contract. This clause basically states that the only person who can change the works information is the Project Manager

So regardless of whether your programme is accepted, what is in the works information remains

 

Member for

17 years 3 months

Dear Gary,



It is always the Contractor’s responsibility to complete the Works as per Contract, specifications, drawings and BOQ even if the Engineer or his/ her representative made a mistake.



The accepted program of works is a tool to monitor the time on the project. It is not a tool to specify the scope. The schedule simply does not fit all the information presented in the Contract, Specification, Drawings and BOQ.



Best Regards,



Samer