Hi to all expertise,
I have updated my schedule now the over all progress is 12.67 % on data date 15-01-2011.
I want to know target percentage for next week of my each WBS as per assinged baseline..
how to show these percentage ?
please need help,,
thanks,,,,,
How to know target Percentage for the next week ?
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Dear Irfan,
if you want to know the target complete % for the next week then go to the projects window there in the dates tab change only the Data Date to the next week but do not schedule..
like this you can get the % complete for the future periods...
Dear Irfan,
if you want to know the target complete % for the next week then go to the projects window there in the dates tab change only the Data Date to the next week but do not schedule..
like this you can get the % complete for the future periods...