Dear Forum,

Could u please urgently show me or advise location(web, URL) of some typical schedule for bridge construction, typical for 4-5 spans with piling, no water no river beneath... please I need urgently...

 

Thanks very much

Carlos

D
Daniel Limson 👤 Member for 24 years 7 months

You normally start with preparing a temporary traffic management or arrangement scheme (TTM or TTA) in the area for approval by the relevant Authorities.

typical construction activities:

1. Piling

2. Pile Load Test

3. Pile Trimming

4. Pile Cap

5. Cast Column

6. Cast Column Head and Bearings

Now it depends what kind of design you have (precast segments (post tension), precast T beams, Cast in Situ, etc.)

7. Say we use precast T Beams lift in place

7. Construct Bridge Deck, Drainage & Parapet

8. Final wearing course and road markings

The construction of the ramps can be done in parallel.

Good luck!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts