Dear Forum,

Could u please urgently show me or advise location(web, URL) of some typical schedule for bridge construction, typical for 4-5 spans with piling, no water no river beneath... please I need urgently...

 

Thanks very much

Carlos

D
Daniel Limson 👤 Member for 24 years 8 months

You normally start with preparing a temporary traffic management or arrangement scheme (TTM or TTA) in the area for approval by the relevant Authorities.

typical construction activities:

1. Piling

2. Pile Load Test

3. Pile Trimming

4. Pile Cap

5. Cast Column

6. Cast Column Head and Bearings

Now it depends what kind of design you have (precast segments (post tension), precast T beams, Cast in Situ, etc.)

7. Say we use precast T Beams lift in place

7. Construct Bridge Deck, Drainage & Parapet

8. Final wearing course and road markings

The construction of the ramps can be done in parallel.

Good luck!

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts