Primavera ver 6.7 is not showing actual percentage why?

I
Irfan Khan 👤 Member for 16 years 10 months

Hi to all experts,

I am working with Primavera 6.7 version & I made a cost & resource loaded schedule.

My schedule’s percent completed type is = Physical & Duration Type is = Fixed Duration & Units.

But while updating the Percentage of schedule it is showing, Schedule % Complete = 22.28% &

Whenever I am transferring the same data to Primavera P3 it showing overall percentage = 4%.

Can anybody tell me why Primavera is not showing actual percentage as P3 shows.

Thanks,

D
Dieter Wambach 👤 Member for 19 years 4 months

Irfan Khan

 

The behaviour of percent complete in P6 is different to P3.

On your Primavera DVD there is a document "Moving From P3 to P6" (or similar). For a better understanding of the differences between P3 and P6 you can study the chapter "Autocost Rules". This will give the answer to your question.

Hope this helps

Regards Dieter

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts