Hi to all experts,
I am working with Primavera 6.7 version & I made a cost & resource loaded schedule.
My schedule’s percent completed type is = Physical & Duration Type is = Fixed Duration & Units.
But while updating the Percentage of schedule it is showing, Schedule % Complete = 22.28% &
Whenever I am transferring the same data to Primavera P3 it showing overall percentage = 4%.
Can anybody tell me why Primavera is not showing actual percentage as P3 shows.
Thanks,
Irfan Khan
The behaviour of percent complete in P6 is different to P3.
On your Primavera DVD there is a document "Moving From P3 to P6" (or similar). For a better understanding of the differences between P3 and P6 you can study the chapter "Autocost Rules". This will give the answer to your question.
Hope this helps
Regards Dieter