Hi
This is simple stuff but I seem to have fogotten and cant find anything in the forum giving exactly the info I need.
I'm pretty new to P6 resources and have a loaded schedule per discipline and I want to take the hours out to produce an S curve.
I want to take hours out by resource over time with actual then budgeted.
The info looks like what you get when you view the resource usage spreadsheet. I used to just copy and paste that into excel from P5 but P6 wont let me do it.
I cant seem to get a report to get the info out in the same way.
Help
Thanks AP PM but this doesnt work.
I cant seem to copy and then paste into excel. If I go to edit, the copy / paste is unavailable to select.
I have always done this without the messing about with running reports. I have 6.0 and aware of some glitches - is this one of them?
Hi Martyn,
Go to Resource Assignment Window, group the activities according to your requirements and at the right pane, show the actual & budgeted units. When done, Edit --> Select All, right click copy & paste it to Excel.
Regards.