Folks, I need help on this.
I have duration type set to fixed duration and units, but when i reassign calendar for a task, it changes the original duration of the task. why is this happening? any ideas?
cheers,
Folks, I need help on this.
I have duration type set to fixed duration and units, but when i reassign calendar for a task, it changes the original duration of the task. why is this happening? any ideas?
cheers,
go to projects directory (big button on left)
make sure that you are have your project highlighted
then view show on bottom Project Details
now look at the calculations tab
then make sure the RESET ORIGINAL DURATION and UNITS to REMAINING button is checked.
now click on the Resources tab
make sure that the DRIVE ACTIVITY BY DEFAULT selection is unchecked in the Assignment Defaults section