REGARDING MS PROJECT ACTIVITY

HAI

friends

i have been created master programme in primavera p6 and i export to ms project 2007 and the programme is developed in ms project now i  need to add activity code in that but i unable to change wbs please help me to solve problem.

 

thanks

 

murali

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Mohana,

there is no such actvity codes in MS Project Standard (stand-alone) (any version) as in Primavera P6; WBS in MS Project is a calculated field you can let as build or set-up.

you could you create a custom field to enter activity codes in it, but you will have some hard time to organize the Gantt Chart from these data.