How can I display the progress agaist the baseline bar?

Hi all,

How can I display the progress agaist the baseline bar?and summarize it?

thanks.

A
Ayman Eleish 👤 Member for 15 years 5 months

Hi Sanad,

Is it possible to update progress in target and reflect it as progress bar for base line,as we used to do it in p3 to compare the current project progress versus the planned progress (blue bar)whether by cost or by time.

S
sanad ahmed 👤 Member for 15 years 6 months

Show schedule% complete againest Performance % complete

Sanad A Ragaee, PMP

S
sanad ahmed 👤 Member for 15 years 6 months

Also you could Show earned value vs planned value cost

Sanad A Ragaee, PMP