Dear PP Members,
1) How does P6 compute for the subtotal of total floats. There is a group consist of 5 activities, 4 activities having total float of 2 days each and 1 activity whose total float = -10days. The group subtotal of total float is -6days.
2) Why schedule variance is not equal to zero reference to a newly created baseline of an "in-progress project''? As far as I know, schedule variance should be zero because the baseline is just the exact copy of the current. Is there a way in P6 to set SV=0?
Thanks in advance.
Merry Christmas!!!
Jerome
Thanks a lot michael.
How do other planning engineers deal with the issue #2 I mentioned above?
'
Hi,
I believe TF = LS - ES or LF - EF of an activity. In a summary of group of activities, TF (summary) equals the TF of the last activity to start or to finish in the group or WBS as Michael said.
regards,
the Rock
TF on summary equals Latest LF minus Latest EF under the wbs code
1) Default Global Calendar affects Total Float on Grouping bands summary
2) No.