Performance % complete to be shown as BL1 Column

Dear All,

Why dont we have a column to choose Baseline perrformance % complete in P6. How can we get a column to show this ?? Any ideas from any expert.

regards,

 

Haresh Jayanth

J
Jerome Soriano 👤 Member for 15 years 7 months

@ haresh,

planned performance % complete @ any given date (data date) is the schedule % complete.

so what you are looking for is exactly the "schedule % complete".

you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost

J
Jerome Soriano 👤 Member for 15 years 7 months

@ haresh,

planned performance % complete @ any given date (data date) is the schedule % complete.

so what you are looking for is exactly the "schedule % complete".

you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost

P
PINAN T. 👤 Member for 18 years 10 months

hi

what do you have in performance % that is not available in schedule %?

they are the same

H
Haresh Jayanth 👤 Member for 19 years 9 months

Dear Jerome,

I want BL1 performance% complete column in the updated program. But P6.7 , doesnt have any provision of having a column as BL1 Performance % complete. The same column can be seen in Updated program i.e. performance % complete. How to get this column , where i can show the planned performance % complete as any given date.

regards,

 

Haresh Jayanth

J
Jerome Soriano 👤 Member for 15 years 7 months

i think you want to see the schedule % complete.

schedule % complete = planned value cost/budgeted cost

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts