Dear All,
Why dont we have a column to choose Baseline perrformance % complete in P6. How can we get a column to show this ?? Any ideas from any expert.
regards,
Haresh Jayanth
Dear All,
Why dont we have a column to choose Baseline perrformance % complete in P6. How can we get a column to show this ?? Any ideas from any expert.
regards,
Haresh Jayanth
@ haresh,
planned performance % complete @ any given date (data date) is the schedule % complete.
so what you are looking for is exactly the "schedule % complete".
you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost
@ haresh,
planned performance % complete @ any given date (data date) is the schedule % complete.
so what you are looking for is exactly the "schedule % complete".
you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost
hi
what do you have in performance % that is not available in schedule %?
they are the same
Dear Jerome,
I want BL1 performance% complete column in the updated program. But P6.7 , doesnt have any provision of having a column as BL1 Performance % complete. The same column can be seen in Updated program i.e. performance % complete. How to get this column , where i can show the planned performance % complete as any given date.
regards,
Haresh Jayanth
i think you want to see the schedule % complete.
schedule % complete = planned value cost/budgeted cost