Week schedule ?

good afternoon to all 

 

the project manager from me to submit to him every week, week schedule show the activities we will work on it , i make filter and i used (early dates ) with the period i wanted, the problem i faced was this condition don't give me all activities that will work through that period i entered, please if there was any error in my work please advice 

 

best regards 

jihad aldoud 

 

D
Daniel Garcia 👤 Member for 15 years 5 months

Hi

Try using this specifications in your filter: 

 

Level 1

Early Start    LT    (Data Date + 7 days)

Actual Start  LT    (Data Date + 7 days)

Level 2

Percent Complete    NE    100%

 

Any questions let me know

Regards

J
Jehad Aldaoud PMP, PMI-SP 👤 Member for 15 years 8 months

Thanks for your reply harzelli, I know i must used filter but the problem is what's the right function must use to get right answer 

H
harzelli bouasria 👤 Member for 17 years 7 months

Hi

simply use spotlight (it's easy), and when print only the requested period.

if u want to show only the activities related to this period use a filter.

Regards

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts