good afternoon to all
the project manager from me to submit to him every week, week schedule show the activities we will work on it , i make filter and i used (early dates ) with the period i wanted, the problem i faced was this condition don't give me all activities that will work through that period i entered, please if there was any error in my work please advice
best regards
jihad aldoud
Hi
Try using this specifications in your filter:
Level 1
Early Start LT (Data Date + 7 days)
Actual Start LT (Data Date + 7 days)
Level 2
Percent Complete NE 100%
Any questions let me know
Regards
Thanks for your reply harzelli, I know i must used filter but the problem is what's the right function must use to get right answer
Hi
simply use spotlight (it's easy), and when print only the requested period.
if u want to show only the activities related to this period use a filter.
Regards