Dear All,
I am having trouble organizing the layout into the WBS code for a project, it seems
unlike P3 where it was automatically organizing as per the WBS code.
Best
Pranab
Dear All,
I am having trouble organizing the layout into the WBS code for a project, it seems
unlike P3 where it was automatically organizing as per the WBS code.
Best
Pranab
dear Jia Qian
What you mean by “you cannot…” even if you know him personally, you should reply accordingly here so that other how don’t know this may get that. Hope you don’t mind it
Mr. Derrick Blunden
Please don’t make this platform an advertising window of your product or web site or some thing. Also don’t waste our time and the space of the site. I would rather suggest the owner or the administrator of the site that please delete such accounts that waste the space with nonsense comments
The post is absolutely fantastic! Lots
logo design of great information and inspiration, both of which we all need! Also like to admire the time and effort you put into your blog and detailed information you offer! I will bookmark your blog and have my children check up here often.
the answer is : you can not...
What a Great Article it its really
custom logo design informative and innovative keep us posted with new updates. its was really valuable. thanks a lot
Dear IAN/Alexandre/Irfan,
Thank you for your response, I did the same actually. I have used group and sort, drop down used wbs level 1 clicked indent and to level 4, now when i select sort bands alphabetically it works.
best regards
Pranab
Hi PKD,
Use the organise'group and sort' Icon to the right of the filter icon,it's plain to see from then on and you will kick yourself.
good luck,
Ian
Hello,
it is very easy too: go to View, Group and Sort; then select WBS in the Group by drop-down list
Alexandre
Hi Pranab
i think ur new in Primavera P6, anyhow, The WBS organization is very easy in compastion of P3.
Here just u hv to define levels of ur work as u defined in P3.
i think u understand.......
Sorry I missed my question, how can i organize the schedule into the wbs layout????????
Sorry I missed my question, how can i organize the schedule into the wbs layout????????