Crane Lifting programs

C
Craig Adams 👤 Member for 19 years 8 months

Hello Fellow Planners,

Has anyone ever produced a detailed crane lift program?

Anyone experienced a contractor who submits one?

Any examples of the above would be appreciated.

Thanks in anticipation,

Craig Adams

M
Mike Testro 👤 Member for 20 years 6 months

Hi Craig

Have a look at my recent post on Hook Time

Best regards

Mike Testro

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Hi Craig,

when we simulate the construction works cranes are assigned to different activities part time. Their percent workload is defined as the ratio of total time of crane usage on some activity to the shift duration. At some activities crane not only lifts but also holds. Resource leveling creates the schedule where cranes are not overloaded though the order of work inside each shift is not defined.

The crane work schedule is practical if you plan the works for short periods like the next shift. Is this your task?

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts