Dear All,
I am having trouble organizing the layout into the WBS code for a project, it seems
unlike P3 where it was automatically organizing as per the WBS code.
Best
Pranab
Dear All,
I am having trouble organizing the layout into the WBS code for a project, it seems
unlike P3 where it was automatically organizing as per the WBS code.
Best
Pranab
you have to be patient because P6 is a new environment but what you're looking for is there and all you need to do is to explore.
cheers,
Right click - Group and Sort - on the top row choose WBS level 1 make sure it is ticked.