Capping the total manhours / day ????

H
Hany Mehany 👤 Member for 15 years 10 months

Hi Guys,

After resource loading the schedule, and having the schedule running for about a year now, the Client is asking us to cap the manpower to a certain number (i.e. 50 persos/day). that would be the maximum number or personnel working on the project. I need to resource level the schedule and get the new dates. how can I do that?

I need to tell the Primavera that the maximum number for hours per day (i.e. 50X10=500 hours/day) then resource level it, any ideas where I can do that?

In the P3 it was from Data -> Resource -> Upper Limit. but can't find it in P6!!!

N
Nikolay Spasibenko 👤 Member for 15 years 7 months

In Resource and Role Libraries the is a file called - Max Units over time set it as 100% for one man/day or 1200% for 12 man days/day

N
Nikolay Spasibenko 👤 Member for 15 years 7 months

In Resource and Role Libraries the is a file called - Max Units over time set it as 100% for one man/day or 1200% for 12 man days/day

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts