Resource loading in P6

K
Kannan CP 👤 Member for 17 years 11 months

Hi friends,

I need to assign the same resource to all activities in P6 schedule. How it can be done using global change? Can anyone advise?

Kannan

S
Sundar Rajan Muthukrishnan 👤 Member for 17 years 2 months

kannan,

Select all activities and right click on mouse you will able to see assign resource click on it then resource window will be opened from that choose the resource which is created for the particular project and then assign it.

Regards,

Sundar Rajan.

S
Stuart Corbett 👤 Member for 17 years 3 months

Highlight 1 activty at the top of your programme, click on the add resource button, highlight every activity that you wish to resource. then simply go back to the assign resource window and add the resource that you require. this will add it to every highlighted activity.

J
James Buxey 👤 Member for 21 years 8 months

Kannan

 

My suggestion is that if you have a common parameter ie the prefix of an Activity ID, or all of the activities have the same activity code you can write a global change that says:

Where [Activity Id contains xx] or [Activity Code equals xx]

Then Resource ID/Name equals xx

The only drawback is that it will automatically default to whatever the available working units are, so if your demand differs from task to task you will have to review once the global change has been done.

 

Regards

James

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts