Hi..

 

Can someone elaborate on Sulfur Recovery Unit commissioning sequence?

 

Abhiyan

M
Mike Testro 👤 Member for 20 years 6 months

Hi Abhiyan

There is nothing special about a programme for an EPC contract.

Every programme should have a design development section leading into procurement and construction - even if the design is being provided by the Employer.