I have trasfered data from SAP to P3 then p3 to p6. I got everything except following:
The budgeted hours and original durations are not same. In p3 valueas are same as SAP but not in P6. I think both values are 8 times more. It may cause of some setting or its the way. Can you please resolve my issue as soon as you can. Otherwise I will have to re assign manualy. There are more then 7000 activities.
Thanks
Minhas
Please make sure the calender definition and hrs per day in P6 & P3 Should be same.
Hi, Just redefine your calender settings and redefine unit hours per day in P6.
Zee.
I've had import messups before and can be a total headache! The first thing I can think of is to check the units/durations you are displaying is using the right time interval - ie. are you showing hours instead of days... the base calendar usually uses 8 hours per day, and you mention the values appear to have been multiplied by 8. Otherwise, check the base calendar default settings are the same between P3 and P6 - eg. both are using 8hrs/day - in the Admin menu, Admin Preferences, Time Periods. Then check activity calendars are being imported, as well as resource calendars. Check the duration type is coming over correctly - changes to type can mean that duration is being used to drive the units, or vice-a-versa.
Hope that helps in some way....!