we need the method statment to know in details how the contarctor will carry out the works (method statment will discrib the main activity in words ad it will includ material , machiery, operation, testing ,risk management, quality control and quality assurance) it will be availabe with the constuction staff o the site after approval in order to do the works o the site acordingly.
we need also constuction program(schedul) i the beging of the project and it shoud iclude all the contract scope of works divided to main activities , subactivitoes, the relation between these activities in proper sequance and logic, the production rate , the required resoureces for each activities..........etc and this program aftre approval will be the -the main tool in the project for monitoring and controlling the progress of works and it has to be up dated weekly or biweekly as per the scale of the project and it will be used for evaluating any claim may submitted by the ontractor for extesion of time .
1)method statement: Its Explain your construction schedule in words,Pictures or using some flow charts...in simple words..its is helpfull for all project team to easily understand which activity when its starting and from where its linked and what are the critical issues bla bla bla....
2)Construction Schedule:Its a logical programm hence only planner or project management level peoples can understand..its is used to schedule,Monitor,Cost control,track alll..in one
Member for
14 years 11 months
Member for14 years11 months
Submitted by waheed mirza on Thu, 2011-01-27 09:30
I think METHOD STATEMENT FOR THE CONSTRUCTION PROGRAMME OR SCHEDULE is different item.
I think in start of any project, baseline schedule is developed & submitted to client, with this baseline schedule there is a document called Programme or Schedule Method Statement. Am I right?
Any one have template or copy of Method statement for the Schedule or Programme?
I think METHOD STATEMENT FOR THE CONSTRUCTION PROGRAMME OR SCHEDULE is different item.
I think in start of any project, baseline schedule is developed & submitted to client, with this baseline schedule there is a document called Programme or Schedule Method Statement. Am I right?
Any one have template or copy of Method statement for the Schedule or Programme?
Regards & Thanks !
Member for
19 years 2 months
Member for19 years2 months
Submitted by ashraf alawady on Fri, 2010-12-03 19:15
please be reminded that the method statment is the the cotractor detailed method of construction ad it will show the cotractor procedures in doig the works and it will show the purpose , the matrials,the equipmets, the methods and sequace of construction,testing , safety measures.
the construction program should be submitted i compliance with clause 14 of the general condito of contract and has also to comply with other cotract requirements it show the logic,sequace ,quantiiyies, duration,resources,production rate,the relation between the activities,the eterface betwee the main parts of the projecct for example iterfane between utilities ad structure ad the utilities ad roads and roads and structure.
it should be sufecintly detailed program to the satisfation of the egineer ad the cliet.
Member for
14 years 11 months
Member for14 years11 months
Submitted by bau-management on Sun, 2010-11-28 08:37
Method statement is submitted by the contractor to the consultant at the beginning of the project for approval. It can also be submitted before the contractor start the work on site. Method statement describes the construction methodology for the work.The method statement encompasses the following:
purpose
scope
references
definitions
responsibilities
equipment / resources
safety
procedure
Bar Chart
Programme shows the logical sequence for the work as defined in the method statement.
Could you please repat it you question, with detail (how would we be able to work together, if we decided to do it in teams?) you mean to say you ahve more planner and you like to divide work load or what....? you can approch to my e-mail to (maqeel2008@hotmial.com)
Member for
19 years 2 monthsDear Mr Khan we need the
Dear Mr Khan
we need the method statment to know in details how the contarctor will carry out the works (method statment will discrib the main activity in words ad it will includ material , machiery, operation, testing ,risk management, quality control and quality assurance) it will be availabe with the constuction staff o the site after approval in order to do the works o the site acordingly.
we need also constuction program(schedul) i the beging of the project and it shoud iclude all the contract scope of works divided to main activities , subactivitoes, the relation between these activities in proper sequance and logic, the production rate , the required resoureces for each activities..........etc and this program aftre approval will be the -the main tool in the project for monitoring and controlling the progress of works and it has to be up dated weekly or biweekly as per the scale of the project and it will be used for evaluating any claim may submitted by the ontractor for extesion of time .
Regards
Member for
13 years 2 monthsanybody is having the airport
anybody is having the airport method statement pls send me too
mail.bipin@yahoo.com
Member for
20 years 2 monthsMr Rayan In layman
Mr Rayan
In layman term,
Method statement - HOW the work to be done
Construction program - WHEN the work to be done
Member for
20 years 2 monthsMr Rayan In layman
Mr Rayan
In layman term,
Method statement - HOW the work to be done
Construction program - WHEN the work to be done
Member for
14 years 11 monthsAssalam alaikum
Member for
14 years 11 monthsPLEASE any planner having the
PLEASE any planner having the template for Schedule method statement and how to present the sequencing
please email me ..i am handling a defence airport project....and very needfull of it.
My email: waheedmirza1@gmail.com
Member for
14 years 11 monthsHi Guys, I think METHOD
Hi Guys,
I think METHOD STATEMENT FOR THE CONSTRUCTION PROGRAMME OR SCHEDULE is different item.
I think in start of any project, baseline schedule is developed & submitted to client, with this baseline schedule there is a document called Programme or Schedule Method Statement. Am I right?
Any one have template or copy of Method statement for the Schedule or Programme?
Regards & Thanks !
Member for
14 years 11 monthsHi Guys, I think METHOD
Hi Guys,
I think METHOD STATEMENT FOR THE CONSTRUCTION PROGRAMME OR SCHEDULE is different item.
I think in start of any project, baseline schedule is developed & submitted to client, with this baseline schedule there is a document called Programme or Schedule Method Statement. Am I right?
Any one have template or copy of Method statement for the Schedule or Programme?
Regards & Thanks !
Member for
19 years 2 monthsDear all, please be
Dear all,
please be reminded that the method statment is the the cotractor detailed method of construction ad it will show the cotractor procedures in doig the works and it will show the purpose , the matrials,the equipmets, the methods and sequace of construction,testing , safety measures.
the construction program should be submitted i compliance with clause 14 of the general condito of contract and has also to comply with other cotract requirements it show the logic,sequace ,quantiiyies, duration,resources,production rate,the relation between the activities,the eterface betwee the main parts of the projecct for example iterfane between utilities ad structure ad the utilities ad roads and roads and structure.
it should be sufecintly detailed program to the satisfation of the egineer ad the cliet.
Member for
14 years 11 monthsHi Rayhan,Method statement is
Hi Rayhan,
Method statement is submitted by the contractor to the consultant at the beginning of the project for approval. It can also be submitted before the contractor start the work on site. Method statement describes the construction methodology for the work.The method statement encompasses the following:
Programme shows the logical sequence for the work as defined in the method statement.
I hope it helps.
Regards,
Puneet Gupta
Bau Management + Consuting GmbH
www.bau-management.info
Member for
16 years 6 monthsDear Mr. Rayan Khan, Could
Dear Mr. Rayan Khan,
Could you please repat it you question, with detail (how would we be able to work together, if we decided to do it in teams?) you mean to say you ahve more planner and you like to divide work load or what....? you can approch to my e-mail to (maqeel2008@hotmial.com)
maqeel
+966599981584
Member for
15 yearsMike, Thank you for that,
Mike,
Thank you for that, just one other question, how would we be able to work together, if we decided to do it in teams?
what sort of problems would we come accross?
Member for
15 yearsMike, Thank you for that,
Mike,
Thank you for that, just one other question, how would we be able to work together, if we decided to do it in teams?
what sort of problems would we come accross?
Member for
19 years 10 monthsHi Rayhan The method
Hi Rayhan
The method statement sets down how the work is going to be cazrried out.
Theprogrtamme stes down the sequence and time that is to completed
The two documents complimet each other.
Best regards
Mike Testro