Tom Jones 👤 Member for 18 years 2 months

Guys,

 

Would like you guys opinion on the easiest way to develop, manage and control an execution master schedule. The schedule will be to level 4 detail, level 4 been the control and cost centre.

Will be using P6. I would like to intergrate about 4 consultant schedules along with interfaces. There isnt any server or network connecting the schedules. Which will be the easiest ways to update the master schedule?

 

Any ideas?

A
Amit Parmar (PMP) 👤 Member for 15 years 6 months

Hey,

Are you comfortable with using multiple projects and inter-relationships between them in Primavera? if your master network is separate from your consultant networks then you can create from LOE activities and link them to your consultant network, which gets updated automatically when the consultant networks get updated.

Its always advisable to have detailed networks seperate cause then you just import the updated file that is sent to you into your existing network and auto update it. Then have these networks connected to your master network to update these files.

It sounds a bit complicated but works. Had the same dilemma when was working on an airport project with 30 sub-packages and subcontractors, it worked their but had its own share of problems too.

Regards

Amit

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts