How to add 50 labours to one activity?

Hello

Imagine we have a task which original duration equal to 7 days

one labour work 10h/day

If I add this labour to the activity the Budget unit become 70=10h*7days

If I want  50 labours working on this activity I have to change the budget unit to 10hx7daysx50labours=3500 isn't it?

Thank you