Imagine we have a task which original duration equal to 7 days
one labour work 10h/day
If I add this labour to the activity the Budget unit become 70=10h*7days
If I want 50 labours working on this activity I have to change the budget unit to 10hx7daysx50labours=3500 isn't it?
Thank you
hi,
I think it is.