Dear all,
I established 4 user number columns and make the following global change:
- Column #1
- Column #2
- Column #3 = 1 x 2
- Column #4 = 3 / 80
But after I run global change columns #3 & 4 still empty and did not include the new values as a result of above formulas.
So please give me the right steps to get the correct and visible values at column #3 & 4 and how I can make this at only this project.
Best Regards,
Abeer
Hi Heba,
Sure I am sure I can help .. I am in Edmonton though ..
Here is my email
[email protected]
Just contact me and we can have a phone chat or messages or to discuss..
hi , mohammad,
My name is heba and i working as planning engineer on Jordan , i have 3 year experience on primavera p3 , but now i am living on Toronto until feb-2011 , i would like to take more course on Canada related to planning can you advice me ?
Best Regards;
Heba
Hi Abeer,
Did you Commit the changes?
After you apply the global change, by clicking (Apply Change), there is a screen that shows you that the global change has been applied and it will show you the results of the change.. Now DO NOT EXIT THIS SCREEN before you click the TAB at the bottom right of the global change screen (COMMITR CHANGES), this will work.... Also, for your quesiton "how can i make it only for this project", do not worry , the global change will be only applied to the current open project only!
good luck
Mohamed
Canada