Good Day all
I am used to working in Primavera and having the luxury of exporting resource spreads into Excel with ease.
How do I do the same using MS Projects 2007.
I want to view the following:
Column A = Task Name or Resource Name of Phase Title etc
Column B = Total Manhours
Column C through to end = Start Month .......all the Way to Finish Month - How the hours are spread.
Please can someone assist me here, I want to avoid having to copy and paste the Resource usage screen from MSP into Excel, too many formats and adjustments to be made.
Please can someone asnwer as soon as possible, it is quite urgent.
Regards
Julian
Eish...so much for that
Hello All...
Anyone willing to offer assistance, I want to be able to use this report quite soons.
Thank you
Regards
Julian
Hi there Rakesh
In 2007, you do not have that function as you did in 2003. You have to use Visual Reports or Export into Excel and use Pivot tables.
How does one get the report exactly in the View or Setup I stipulated?
Thanks
Kind Regards
Julian
Julian you can try it for MSP 2007 i had used it in MSP 2003
It is very simple
go to Tools>>Customize>> toolbars>> and select for "Analysis" toolbar
And use "Analyze Timescaled data in Excel"
Regards
Rakesh Baurai
[email protected]
[email protected]
+919724348356
Julian you can try it for MSP 2007 i had used it in MSP 2003
It is very simple
go to Tools>>Customize>> toolbars>> and select for "Analysis" toolbar
And use "Analyze Timescaled data in Excel"
Regards
Rakesh Baurai
[email protected]
[email protected]
+919724348356