Good morning,
i have problem when primavera 6.7 calculate the duration at summary level -wbs
as i have to change admin preference - time period
and this affect other projects
how can we let primavera calculate duration at WBS level for each project according to project's calendar
as example now - wbs first activity start on 2-Nov
last activity finish 2-dec
so duration should be 30 days
but it shows only 10 days
i don’t know how
Hi,
I write an article regarding How does Primavera P6 summarize data in the Summary / Grouping Band. If you're interested kindly read here https://doduykhuong.com/2017/07/10/how-does-primavera-p6-summarize-data-in-the-summary-grouping-band/
hi, all
When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar.
Best Regards
in P6 version 7 ,,,, you have to have tick a global default calender,
may next version have this option which you wants,
make default global equals project calendar
in p6v7 project calendar can be tick as basis of summary
Thanks Michael
is there alternative way to avoid using default calendar
check your assigned global calendar
p6 summary duration are based on global calendar (not project)
check your assigned global calendar
p6 summary duration are based on global calendar (not project)