how primavera calculate summary duration -wbs ?

A
Alaa Al haj 👤 Member for 18 years 7 months

 

 

Good morning, 

 

 

i have problem when primavera 6.7 calculate the duration at summary level -wbs

as i have to change admin preference - time period

and this affect other projects

how can we let  primavera calculate duration at WBS level  for each project according to project's calendar

as example now - wbs first activity start on 2-Nov

last activity finish 2-dec

so duration should be 30 days

but it shows only 10 days

i don’t know how  

N
niles luo 👤 Member for 20 years 6 months

hi, all

    When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar.

Best Regards

S
Shazia khan 👤 Member for 18 years 1 month

in P6 version 7 ,,,,  you have to have tick a global default calender,

may next version have this option which you  wants,

M
michael ramos 👤 Member for 17 years 3 months

make default global equals project calendar 

in p6v7 project calendar can be tick as basis of summary

A
Alaa Al haj 👤 Member for 18 years 7 months

Thanks Michael 

 

is there alternative way to avoid using default calendar

M
michael ramos 👤 Member for 17 years 3 months

check your assigned global calendar

p6 summary duration are based on global calendar (not project)

M
michael ramos 👤 Member for 17 years 3 months

check your assigned global calendar

p6 summary duration are based on global calendar (not project)

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts