Schedule analysis & Time impact analysis

I have read somewhere about schedule analysis & Time impact analysis.Can anyone explain what are those and How & when to perform them on a schedule and  advantages of  them.

P
praveen verma 👤 Member for 15 years 5 months

can anyone explaim me in details step for prepating time impact analyis !! 

N
Naveen Paladugu 👤 Member for 15 years 11 months

Thank you Mike for your informative reply. It made my concepts clear. I have been using it with out knowing the name of it. Could please provide any documents/files reg. that. I am happy to hear from you.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Naveen

Daniel has given you a good explanation regarding time impact analysis but it is not that simple.

You should only use time impact analysis for work in progress.

If something has happened to hold up the work you need to put in a task that represents the delay period.

Save the file under a new name.

You should then link the delay to the delayed activities and reschedule to see what happens to the end date.

The method only works if you have a fully detailed bottom up programme that responds realistically to impacted events.

If your programme is full of FF SS Links - lead lags - constraints etc then you will get a misleading response.

Remember that the result is always theoretical and will change as circumstances change.

Best regards

Mike Testro

N
Naveen Paladugu 👤 Member for 15 years 11 months

That means we can make use of time impact analysis when we seek EOT, right?. got it. Thanks a lot for your valuable information

D
Daniel Limson 👤 Member for 24 years 7 months

Hi Naveen,

Okay let me explain further, the term "Time Impact Analysis" means you are assessing or analysing the impact of a certain activity or event and how it affects the programme, especially your contractual critical dates and/or completion dates. These are normally used to see the impact of change orders or variations or any unforseen event which caused a delay.

What if analysis are more like a programme study or programme analysis of various scenarios, so it helps the managment to decide and select the best option.

Best regards,

N
Naveen Paladugu 👤 Member for 15 years 11 months

Thank you for your reply. I am satisfied with your reply reg. schedule analysis but for time impact analysis, could you explain in what situations we use it and how to perform (means can we do it through what-if analysis??)

D
Daniel Limson 👤 Member for 24 years 7 months

Schedule analysis could just be about anything in the programme, a thorough schedule analysis would mean reviewing the following:

Logic and sequence of works

Duration and produciton rates

Quantities

Project contraints

Procurement and delivery of long lead items

Calendar usage

critical path

Milestones and Key Dates

On the other hand, "time impact analysis" nornally talks about an event or group of events and their impact or effect on the programme especially on critical key dates.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts