Physical % complete
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
You could try for Duration % Complete.
P3 also uses the same criteria to show the overall %
--------
Regards,
Sajeeth
You could try for Duration % Complete.
P3 also uses the same criteria to show the overall %
--------
Regards,
Sajeeth
kim,
Physical % rolled up to WBS Level-1 is not worked in P6 as of now, may be next version we will have this option,
so you may chose other option. Performance Complte nad schedule % complate ,so on.
Try using a different column to display the % complete.
Such Performance % Complete