Difference between Piping and pipeline, what is Pipeline project and what is cross country pipeline project.

S
Shazia khan 👤 Member for 18 years 1 month

Hi All

 

I would like konw , basic about pipeline project,

 

what is cross country Pipeline Project, and pipeline project.

 

Best Regards

 

S
Shazia khan 👤 Member for 18 years 1 month

Alex,

 

Thanks for your explanation this is rely what i was looking for,

 

construction Sequence. (please correct me if i am wrong)

Piping- Fabrication

Pipe sand Blasting painting                                           

Marking and Bevel cutting.

Welding

NDT

Hydrotes (spool testing.)

Installation if Ground piping if,

Erection.

Erection on the Pipe rack

Welding erected spool pipe

NDT

Hydro test

Chemical cleaning / passivation.

Insulation

or final coat paint.

Pipeline:

Stringing of the pipe (on trench Side)

Welding

NDT

wrapping Coating or insulation of pipe Joint

Lower the pipe in the trench

Back filling of Trenched

Pig Cleaning

Ready for operation.

Please advise me if this correct sequencing.

A
Alex Iskandar 👤 Member for 22 years 5 months

hi Shazia, Just for share the knowledge, as I just arrived to this forum ...

Yes Daniel is right, they all pipes, but to increase our knowledge and just want to share what I've learn from the course

(If you are an engineer don't hesitate to ask your manager for getting more training in Engineering, to have training such as Piping and pipeline design etc, would increase your skills for planning)

Piping Terminology;

  1. Transmition pipelines: Usually long, relatively large diameter lines, May Tranport Hydrocarbon fluids and or Gas. from prudocing fields to processing plant or refineries.. From plants and refiniries to marketing centers
  2. Flowline: Two phase lines (Non separted HC with two phase (liquid and gas) flows before entering the inlet separator), connecting welss to production manifolds. range from 2 - 20 inches.
  3. Trunkline: Two or more well flowlines connected to a larger line that carries the combined well stream to the production manifold. range from 10 to 42 inches.
  4. Injection lines: Transport high pressure gas or water to wellheads for injection into the producing formation. Fluids are injected for: Reservoir pressure performance, production enhancements, conservation of gas, Gas Lift, Produced water disposal , waterflood, steam flood.
  5. Piping / Plant (Facility) Piping (on plot) : Piping witihin the well defined boundaries of the processing plants, piping compression station or pumping station. Used for a variety of fluids within those boundaries as required.

Warmest regards from Indonesia

Alex Iskandar, PMP

D
Daniel Limson 👤 Member for 24 years 8 months

Shaza Khan,

I do not see any difference at all, they are all pipes to me.

As a planner, what you need to know is basically the diameter of the pipe, the lenght of the pipeline and your welding production rates. You also need to know whether it is above ground or underground. If it is underground you need to know the soil conditions, where the pipe is being laid. If it is above ground you need to construct pipe sleepers to protect the pipe. You need to look at the scope of work. Does it require cathodic protection? Does it require insulaton or painting?

If the pipeline is for Gas or Oil you may need to know about cold cutting and tie-in procedures.

Best regards,

Daniel

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts