Go to Resource Usage view and define a new filter “Resource Base Calendar is Night Shift” where;

  • Field Name = Base Calendar
  • Test = equals
  • Value(s) = Night Shift

It will display only activities with assigned resources whose base calendar is Night Shift. Therefore, in order to identify night shift activities these must already have been assigned a resource with a night shift base calendar. If you want to exclude activities with assigned calendar resource, exclusively a night shift then you shall expand your filter as to exclude those.

You can create a Combination View with a Primary View equal to Resource Usage and a Details Pane equal Gantt Chart, there you can apply the filter on the upper pane and select the activities on the lower pane.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts